Sonuç bulunamadı!...
TAYSEB Substation
Employer
TAYSEB
Scope of Work
Turnkey EPC contract including Design, Engineering, Procurement, Supply, Installation Testing and Commissioning of 154/31.5kV Downstream Substation for the connection of a poultry factory to the electricity grid in Adana, Turkey
Sector
Industry
Location
Adana, Türkiye
Project Duration
May 2021 - May 2022

About Project

Turnkey EPC contract including Design, Engineering, Procurement, Supply, Installation Testing and Commissioning of 154/31.5kV Downstream Substation for the connection of a poultry factory to the electricity grid in Adana, Turkey.

News
As Kontrolmatik Teknoloji, we aim to continuously enhance stakeholder value through the implementation of corporate governance in investor relations, in line with international standards.
View all