Within the scope of the Ouagadougou 50 MW Heavy Fuel Oil (HFO) Diesel Power Plant project, Kontrolmatik delivered the turnkey engineering, design, supply, installation, testing, and commissioning of the plant’s complete electrical systems, as well as the automation and control infrastructure. The implemented solutions enabled safe, reliable, and efficient operation of the power plant.
Within the scope of the construction of a new terminal to support the existing terminal, the installation and commissioning of the SCADA Energy monitoring system in this new terminal and the configuration of the Network system, communication and RTUs were carried out.
Engineering, Design, Manufacturing, Supply, Installation, Testing and Commissioning of MCC and PLC Panels, Instrumentation and Piping, Civil Works and Civil Engineering, CCTV and Security Systems, Process Equipment and Central Control Room Automation, Modernisation and Rehabilitation works at ISKI Kağıthane Water Treatment Plant.
Installation of 500 kW/500 kWh Battery Electricity Storage Systems Including Installation and Network Connections to MEDAŞ General Directorate.
Supply, Installation and Test Commissioning of 6 MWp Rooftop Solar Energy for MAN Turkey factory.
EPC High Voltage Substation
Turnkey EPC contract including Design, Engineering, Procurement, Supply, Installation Testing and Commissioning of 154/31.5kV Downstream Substation for the connection of a poultry factory to the electricity grid in Adana, Turkey.
Within the scope of the Kirazlık Hydroelectric Power Plant Automation and Electrification Systems project, Kontrolmatik delivered the engineering, design, supply/manufacturing, installation, testing, and commissioning of the generator and transformer protection systems, low-voltage switchboards, MCC panels, synchronization system, battery–UPS system, and the SCADA system. The integrated automation and electrification solutions ensured safe, reliable, and high-efficiency operation of the power plant.
Turnkey Reducing Mobile Substation with 33kV/11kV voltage and 31.5MVA power
Within the scope of the Enerjisa Erciyes WPP project, Kontrolmatik delivered the engineering, supply, installation, and commissioning of the 154 kV substation, fiber optic (FO) cable system, grounding conductors, as well as the 34.5 kV electrical, communication, control, and grounding systems. The project ensured safe, reliable, and standards-compliant grid integration of the wind power plant.
Engineering, Design, Supply, Installation and Testing and Commissioning of Medium Voltage Switchgears, Low Voltage Switchboards, High Voltage Power Transformers, SCADA Control System, DC Switchboards and DC System and UPS System
Within the scope of the Garoua–Maroua Substations project, Kontrolmatik delivered the design, supply, and installation of high-voltage substations. The project contributed to strengthening the regional power transmission infrastructure by ensuring reliable, safe, and standards-compliant electricity distribution.
Turnkey Mobile Substation with 132kV/11kV voltage level and 25MVA power rating
Turnkey Reducing Mobile Substation with 33kV/11kV voltage and 16MVA power for Distribution Reinforcement in Electricity Grid
Within the scope of the Uşak RES 154 kV Feeder Extension project, Kontrolmatik carried out the addition of one transformer feeder, the addition of two line feeders, and the revision of one transformer feeder. The project also included all civil works within the switchyard, installation and erection of primary and secondary equipment, as well as grid connection and synchronization. As a result, the facility was successfully integrated into the grid in a safe, reliable, and standards-compliant manner.
Within the scope of the 110 kV Power Transmission Line and Substation project, Kontrolmatik delivered the turnkey construction of a 20/90 kV step-up substation with a capacity of 2×24 MVA, along with a 14 km overhead transmission line. The project covered all engineering, supply, construction, installation, testing, and commissioning activities, ensuring reliable and secure power transmission in full compliance with applicable standards.
Engineering, Design and Manufacturing
Engineering, Design and Manufacturing
Turnkey High Voltage Substation with 132/11kV voltage Turnkey High Voltage Substation in Bazian, Iraq.
Within the scope of the KfW Lot-1 Mosul Substations project, Kontrolmatik delivered the turnkey engineering, design, manufacturing, supply, installation, testing, and commissioning of three air-insulated substations (AIS) and one gas-insulated substation (GIS) at the 132/33 kV voltage level in Mosul, Iraq, financed under the KfW fund. The project significantly strengthened the region’s power transmission infrastructure, ensuring safe, reliable, and sustainable electricity supply.
Dismantling and rehabilitation of the Warning System for Turboalternator with 4MVA power in Eti Maden Plant, Dismantling of existing panels, Engineering, Design, Manufacturing, Assembly and Testing and Commissioning of 2 Sets of Compensation Panels.
Construction of a Turnkey Substation with a capacity of 2x50MVA at 132/33kV Voltage including Engineering, Design, Manufacturing, Procurement, Installation and Testing and Commissioning within the scope of grid connection of a steel production facility in Kalar, Northern Iraq.
Within the scope of the Tedzani IV HPP project, Kontrolmatik delivered the Electrical Balance of Plant (EBoP) package for the Tedzani IV Hydropower Plant in Malawi, covering the complete electrification of the plant. The scope of work included the engineering, supply, installation, testing, and commissioning of the high-voltage substation and the high-voltage transmission line. As a result, the plant was equipped with a safe, efficient, and internationally compliant electrical infrastructure.
Complete electrification of Faizabad Hydro Power Plant in Afghanistan within the scope of EBoP (Electrical Balance of Plant) Package.
Combined Cycle Natural Gas Power Plant in Khorazm, Uzbekistan Complete electrification of the plant, 220kV High Voltage Substation and Transmission Line within the EBoP (Electrical Balance of Plant) Package.
Within the scope of the Cenergo CCPP 220 kV Substation and Underground Cable Line project, Kontrolmatik delivered the turnkey engineering, design, manufacturing, supply, installation, testing, and commissioning of a 220 kV substation for a 240 MW Combined Cycle Natural Gas Power Plant located in Uzbekistan. The project ensured a safe, reliable, and continuous grid connection of the power plant through a high-voltage infrastructure implemented in compliance with international standards.
Turnkey Substation construction at 110kV Voltage including Engineering, Design, Fabrication, Procurement, Supply, Installation and Testing and Commissioning for 470MW Combined Cycle Natural Gas Power Plant and Overhead transmission line in Tashkent, Uzbekistan.
Complete electrification of 50MW Dual fuel (Gas/HFO) power plant in Walvis Bay Namibia within the EBoP (Electrical Balance of Plant) Package.
110/20kV Turnkey Step Up Substation including Engineering, Design, Fabrication, Supply, Installation and Testing and Commissioning for Solar Power Plant in Oslomej, North Macedonia
Complete Rehabilitation and Electrification with Complete Engineering, Design, Procurement, Supply, Installation and Testing and Commissioning of High Voltage, Medium Voltage, Low Voltage Systems, Substation Transformer, Switchgears, UPS Systems, SCADA Systems and Telecommunication Systems for Kenya Gitaru Hydroelectric Power Plant.
IEC 61850, SCADA, RTU, Communication System and Panel Supply, Commissioning and Supervision Works
Within the scope of the Yarımca Port RTU and SCADA System project, Kontrolmatik delivered IEC 61850–based SCADA and RTU systems, including the supply of communication systems and control panels, as well as commissioning and control activities. The implemented solution enabled reliable real-time monitoring, control, and secure operation of the port’s electrical infrastructure through an integrated and standards-compliant automation system.
Üsküdar–Çekmeköy Metro Line project, Kontrolmatik delivered the Tunnel Ventilation Control System and Central Control Room solutions for tunnels and stations. Within the scope of the project, automation infrastructure, monitoring and control scenarios, and central SCADA integration of the ventilation systems were implemented. The deployed solution ensures operational continuity, passenger safety, and effective emergency management through a fully integrated and reliable control system.
MCC-ECS Environmental Control System
Tunnel Ventilation Control System
EPC 400 kV GIS Substation
EPC High Voltage Substation
Within the scope of the North Marmara Natural Gas Storage Expansion Project, Kontrolmatik delivered the engineering, construction, installation, testing, pre-commissioning, and commissioning of the electrical, instrumentation, and control (EIC) systems covering the onshore facilities, New Surface Facility (NSP), North Marmara Gas Field (NMGS), offshore platforms, and the BOTAŞ connection. The project significantly enhanced the operational capacity, safety, and reliability of the natural gas storage facility in full compliance with international standards.
Panel Manufacturing, SCADA and Secondary Systems Installation.
IEC 61850, HEPP 154kV Substation, Control System, Secondary and Communication System, Supply and Supervision works.
Renewal of the warning system of two 2720 kVA generators, renewal of the synchronization system, renewal of the generator protection system, replacement of generator output breakers, installation of energy monitoring system (SCADA), installation of battery / rectifier and power supply system (for both generators).
Within the scope of the Nuri Şeker Uşak Sugar Factory project, Kontrolmatik delivered the engineering, installation, and commissioning of the synchronization, load taking–load shedding automation, protection and alarm systems, and the SCADA system for the Steam Turbine – Turbo Generator Group. Through this project, safe, reliable, and efficient operation of the power generation processes was ensured, and the plant operations were equipped with a centralized and fully integrated control infrastructure.
Installation of Electrical Systems and Automation System of Dehydrated Borax II Plant in Eti Maden Kırka Facilities.